Soliswitch FTE20 Commissioning
Endress+Hauser 19
7 Commissioning
7.1 Post-installation and post-connection check
Checklists:
Post-installation check →  13
Post-connection check→  16
7.2 Setting the switching pressure (sensitivity)
The switching threshold can be adapted to the weight of the bulk solids in 3 stages via an
operating element that is accessible from above (also possible during operation):
Minimum: 80 g/l (4.99 lb/ft³)
Adjustable in 3 stages depending on the density of the bulk solids: low, medium (factory
default), high
7.3 Switching on the device
The shaft starts to turn as soon as the supply voltage is switched on. The rotational movement
can be observed from the outside.
*Option
A0017353
 15 Window to observe rotational movement
8 Troubleshooting
Functional testing of the point level switch by testing the internal switch →  14,  18