233 
Calibration Information
 
12 
Testing the Display 
Push K and turn the rotary switch to the e position. Compare the display with the example in Figure 6. 
Check all segments for clarity and contrast. 
 
erc022f.emf 
Figure 6. Display Segments 
Backlight Test 
To Test the Backlight, press Q and verify that the backlight comes on. 
Keypad Test 
To test the keypad, turn the Meter to ACV and push each button separately. Each button push should cause the 
Meter to beep and activate a display annunciator. 
Reset the Meter by turning it Off and then back to an on position. 
Preparing for the Performance Tests 
XWWarning 
To avoid possible electric shock or personal injury: 
•  Do not perform the following procedures unless qualified to do so. Some 
procedures involve the use of high voltages. 
•  Before handling the test connections and in between tests, make sure 
the calibrator is in standby mode (STBY). 
To prepare for the performance test: 
1.  Make sure that you have the required equipment (refer to Table 2). 
2.  Warm up the calibrator as required by its specifications. 
3.  Allow the temperature of the UUT to stabilize at room temperature (23 °C ± 5 °C [73 °F  ± 9 °F] ). 
4.  Check the fuses and Battery, and replace them if necessary. Refer to “Fuse Test”, and “Fuse 
Replacement”. 
To verify the accuracy of the Meter functions, do the following: 
1.  Connect the Calibrator to the VΩ and COM input terminals on the Meter. 
2.  Turn the rotary switch to the function listed in each step of Table 3.