DFA400 Rev150730
14
Weldment Installation
Note: Ensure that the mounting location meets the requirements for uniform
water ow. (Refer to Flow Sensor Location Guide.)
Note: Ensure that there is enough room for the weldment, sensor, and
connector to t. (Refer to Figure 5.)
1. Drill and deburr a 1 11/16" to 1 3/4" diameter hole at mounting location.
2. Center weldment mount over hole and weld it to pipe. The weld must be
continuous around the tting with no gaps or voids.
3. Screw sensor housing into weldment far enough to make sure it goes through
the pipe freely, then back it out.
Note: The paddlewheel sensor must be correctly aligned in the water
stream. The alignment tab is used to set the sensor position. Make sure
the alignment tab is centered on the pipe center line. (Refer to Figure 5.)
4. Set sensor housing to dimension A in Figure 5. Make sure alignment tab is
centered on the pipe as shown (it can be on upstream or downstream side).
5. Install Tru-Seal locknut and tighten with 2" wrench using light to medium
torque. Make sure the sensor housing alignment tab remains centered and the
sensor housing does not rotate causing dimension A to change.
6. Insert ow sensor into sensor housing. Align at spot on sensor rim with
alignment tab and make sure O-ring is in groove.
Note: The retainer cap is hand-tightened. There is an inside lip that stops
the cap from turning when it makes contact with the alignment tab. This
provides the correct pressure to make the seal at the O-ring. Make sure
the ow sensor engages the alignment tab and does not rotate.
7. Install retainer cap and hand-tighten.
8. Connect cable from display module to ow sensor (cable is color coded blue).
(Refer to Wiring Section.)