READ THIS FIRST: COMPRESSOR PRESTART CHECKLIST
The installer must check and complete the following items before the arrival of the FRICK Field Service
Supervisor. Details on the checklist can be found in this manual. Certain items on this checklist are reveried
by the FRICK Field Service Supervisor before the actual start-up.
Mechanical Checks
__ Package installed according to FRICK publication
070.210-IB, Screw Compressor Foundations.
__ Conrmthatmotordisconnectisopen
__ Isolate suction pressure transducer
__ Pressure test and leak check unit
__ Evacuate unit
__ Remove compressor drive coupling guard
__ Remove coupling center and DO NOT reinstall
(motor rotation must be checked without center)
__ Check for correct position of all hand, stop, and check
valves PRIOR to charging unit with OIL or REFRIGERANT
__ Charge unit with correct type and quantity of oil
__ Lubricate electric drive motor bearings PRIOR to
checking motor rotation
__ Check oil pump alignment (if applicable)
__ Check for correct economizer piping (if applicable)
__ Check separate source of liquid refrigerant supply (if
applicable, liquid injection oil cooling)
__ Check water supply for water-cooled oil cooler (if ap-
plicable, water cooled oil cooling)
__ Check thermosyphon receiver refrigerant level (if ap-
plicable, thermosyphon oil cooling)
__
Check for PROPER PIPE SUPPORTS and correct foundation
__ Check to ensure ALL piping INCLUDING RELIEF VALVES
is completed
After the above items have been checked and veried:
__ Close the main disconnect from the main power supply to the motor starter
__ Close the motor starter disconnect to energize the micro
__ Manually energize oil pump and check oil pump motor rotation
__ Leave micro energized to ensure oil heaters are on and oil temperature is correct for start-up
__ DO NOT energize compressor drive motor! Only authorized Factory Field Service Technicians are to perform this.
Summary:
Ensure the above items are completed for when the FRICK Field Service Supervisor arrives
.
Ensure there is an
uncoupled compressor drive unit (to verify motor rotation and alignment) and energized oil heaters with the oil at the
proper standby temperatures
. Full compliance with the above items contributes to a quick, efcient, and smooth start-up.
The Start-up Supervisor:
1.Veriespositionofallvalves
2.Veriesallwiringconnections
3.Veriescompressormotorrotation
4.Veriesoilpumpmotorrotation
5.VeriesthepercentageofFLAonthemicrodisplay
6.Veriesandnalizesalignment(ifapplicable)
7. Calibrates slide valve and slide stop
8. Calibrates temperature and pressure readings
9. Corrects any problem in the package
10. Instructes operation personnel
NOTE: Customer connections are to be made as illustarated in the electrical diagram for the motor starter
listed under the installation section and the wiring diagram listed under the maintenance section of the
IOM.
Complete and sign this form and fax to 717-762-8624 as conrmation of completion.
FRICK Sales Order Number: _____________________
Compressor Model Number: _____________________
Unit Serial Number: ____________________________
End User Name: _______________________________
Address of Facility: _____________________________
City, State, Zip: ________________________________
Print Name: ___________________________________
Company: _____________________________________
Job Site Contact: _______________________________
Contact Phone Number:_________________________
Signed: ______________________________________