Dynamic power
regulation with
several inverters
Example 1: Fronius SnapINverter ≤ Fronius Symo GEN24 SC
Only one primary meter is required for the Fronius Symo GEN24 SC inverter.
The power values shown are an example. Inverter configurations with power val-
ues other than those shown in the example are possible, taking into account the
criteria for this example.
IMPORTANT!
Zero feed-in is not possible when using two inverters.
P
AC nom
= 9 kW
P
AC nom
= 12 kW
+
-
00
1
6
7
1
Settings on the user interface of the Fronius Symo GEN24 SC inverter:
1
Configure the primary meter at the feed-in point in the "Device configura-
tion""Components" menu.
2
Activate the limit for the entire system in the "Safety and grid regulations"
"Export limitation" menu. Enter the DC rated power of the entire PV system
in the "Total DC system power" input field. Enter the percentage value (50%,
60% or 70%) in the "Maximum permitted feed-in power of the entire system"
input field.
Example 2a: Fronius SnapINverter > Fronius Symo GEN24 SC
Two primary meters are required for the inverters.
The power values shown are an example. Inverter configurations with power val-
ues other than those shown in the example are possible, taking into account the
criteria for this example.
IMPORTANT!
With two primary meters at the feed-in point without a secondary meter, Fronius
SnapINverter and Fronius Symo GEN24 SC inverters cannot be displayed as a
combined PV system in Solar.web. Two individual PV systems must be created in
Solar.web.