Note
Assembly should be completed within 20 seconds after last application of cement.
Do not use hammer to insert pipe.
8. After assembly, wipe excess cement from pipe at end of fitting socket. A
properly made joint will show a bead around its entire perimeter. Any
gaps may indicate a defective assembly due to insufficient cement.
9. Handle joints carefully until completely set.
18. Intake Muffler Installation
a) Follow steps 1-9 above for cementing joints. For best noise attenuation, the muffler
should be installed as close to the boiler as possible.