Appendix A. Checklist for Use of EP-19xx Modules
GFK-2956A November 2017 69
Appendix A Checklist for Use of EP-19xx Modules
Checklist for use of EP-19xx Modules
Equipment type / equipment ID
The corresponding manual was consulted during planning.
The sensors/control devices are approved for connection to the
module.
The power supply was planned as per the safety extra-low
voltage guidelines in accordance with PELV or SELV.
The module was externally fused according to the guidelines in
the manual.
Measures to prevent simple manipulations have been planned.
Measures against plug mix-ups have been planned.
The requirements for the sensors and installation of cables
correspond to the applicable safety standards (SIL, Cat., PL) and
the planned implementation takes these standards into
consideration.
The guidelines for per-channel configuration have been defined.
The intentional starting up of potentially hazardous processes is
only possible while looking into the danger zone at the same
time.
If the installation requires exclusions of faults: the measures
have been realized.
The planned use corresponds to the intended use.
The environmental conditions meet the guidelines that are
specified in the technical data.
The accessories to be used were selected according to the order
data in the manual.
The guidelines for installation and electrical set-up were defined
and handed over to the departments performing the work.
The guidelines for commissioning were defined and handed over
to the departments performing the work.
Date / Signature of Reviewer 1:
Date / Signature of Reviewer 2:
Checklist for use of EP-19xx Modules