OPM_SGS_USM_10K_40K_0US_V010.doc 51/88 Operating Manual
SG Series
10, 20, 30 & 40 kVA
7.2.3 Restore to normal operation after “total off”
View of the panel after pressing the
button “total off”.
All Contacts are open;
Rectifier, Inverter and Static-Switch
shutdown.
1. Reset total off by pressing and
holding the “total off button and the
inverter on
( I )
key simultaneously
until the Rectifier starts.
2. Connect the Battery to the UPS by closing the Battery Switch or Fuses, in case
of External Battery.
3. Press
inverter on
( I ) key
.
Soft-start of Inverter indicated with
blinking LED.
At the end of Soft-start the LED
remains lit.
UPS output LED indicates Load on
Inverter.
The LCD must display on the main screen the status LOAD ON INVERTER.
End of procedure