GE_UPS_USM_TLE_SUL_M16_M50_2bU_V010.docx
User Manual TLE Series 160 - 500 UL S2B
During the first commissioning TLE Series 160 - 500 requests a set-up of the UPS configuration
parameters presented in the following “Power-Up” screen.
Without such configuration it is not possible to continue with the commissioning procedure.
WARNING !
The set-up of the UPS configuration parameters must be done only by a GE Service
Technician.
The set-up of mistaken values could compromise the integrity and reliability of the
UPS.
This parameter allows the choice of language used to display the
information.
You can adjust the date of the real time clock existing in the UPS by the
means of this parameter.
The value you enter is thoroughly checked to be a correct date in the
You can adjust the time of the real time clock existing in the UPS by
means of this parameter.
The value you enter is thoroughly checked to be a correct time in the
format “hh.mm.ss”.
The time is specified in 24-hour format.
Input frequency value (50 Hz / 60Hz).
Inverter output frequency value (50 Hz / 60Hz).
Output voltage PHASE/NEUTRAL of the Inverter (277V).