8. Safety checks on electrical systems
8.1 Safety checks on electrical systems according to BGV A2, imple-
mentation instruction clause 1 No.2
8.1.1 Repetitive checks on stationary electrical systems and operating equipment
Attention: Let any eventual repairs at the electric drive carried out by an electrician
(specialist, specialised work shop) or by Gölz GmbH!
System/operating equipment Inspection
period
Type of inspection Inspector
Electrical systems and stationary
operating equipment
4 years For proper condition Specialist electrician
Electrical systems and stationary
electrical operating equipment in
"Special business premises, rooms
and facilities"(DIN VDE 0100 Grup-
pe 700)
1 year
Protective measures with fault cur-
rent protection facilities in non-stati-
onary systems
1 month For effectiveness Specialist electrician or
person trained in elec-
trical engineering, using
suitable measuring and
test equipment
Fault current, differential current
and fault voltage circuit breakers
- in stationary systems
- in non-stationary systems 6 months
Each working
das
For fl awless function by
actuating the test facility
User
8.1.2 Repetitive checks on mobile electrical systems and operating equipment
System/operating equip-
ment
Inspection period
guideline and maxi-
mum values
Type of inspec-
tion
Inspector
- Mobile electrical operating
equipment (if used)
- Extension and device con-
nection cables with plug
devices
- Connection cables with plugs
- Moveable cables with plug
and fi xed connection
Guideline value 6
months, 3 months on
construction sites.
If a fault rate of <2% is
achieved during the in-
spections, the inspection
period can be extended
accordingly.
Maximum values:
On construction sites,
in production plants
and workshops or under
similar conditions, one
year,
in offi ces or under simi-
lar conditions, two years
For proper condition Specialist electrician or
person tained in electri-
cal engineering, using
suitable measuring and
test equipment