Page 36 Section 10: Commissioning
10 COMMISSIONING
To ensure safe and ecient operation, it is essential that a Grant
Vortex Eco boiler is commissioned as detailed in the following
procedure.
To access the controls, remove the front door from the boiler
casing (pull forward at the bottom and then lift o).
The controls are shown in Figure 10-1 and the boiler components
are shown in Figure 10-2.
Figure 10-1: Vortex Eco boiler control panel
Casing Door locating channels
Lock-out button
Control Panel
Figure 10-2: Position of boiler components - Vortex Eco External boiler