EasyManuals Logo

Gree GMV5 Service Manual

Gree GMV5
321 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #141 background imageLoading...
Page #141 background image
GREE Photovoltaic Direct-driven Inverter Multi VRF Units
137
Note: During commissioning, users must listen to the operating sound of outdoor and indoor fans
and compressors to check for exceptions.
(3) Commissioning Through the Portable Commissioning Tool
Step 1: Connect the Portable Commissioning Tool. Please refer to the operation manual of Portable
Commissioning Tool for the connection method.
Step 2: Setting DIP of ODU address. You must set this DIP in main control ODU. The setting code
(SA8) of main control unit shall be set to “00”. Otherwise, it is invalid.
Step 3: On the home page, press Unit Debug to enter into the page of engineering debugging.
Step 4: On the engineering debugging page, click “Startup” button to start engineering debugging;
press “Stoppage)” button to pause the engineering debugging;

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Gree GMV5 and is the answer not in the manual?

Gree GMV5 Specifications

General IconGeneral
BrandGree
ModelGMV5
CategoryInverter
LanguageEnglish

Related product manuals