GREE Photovoltaic Direct-driven Inverter Multi VRF Units
19
If the pipe needs to go through a bearing beam, a steel casing must be prepared.
1.3.2 Requirements for cooperation with decoration engineering
The air conditioning installation should not damage the bearing structure or the decorative style. Air
conditioning pipes should be laid out along the bottom of the beam as possible. If pipes meet one
another at the same elevation, process based on the following principles:
(1) Drain pipes enjoy the highest priority. Air ducts and pressure pipes should leave places for
gravity pipes.
(2) Air ducts and small pipes should leave places for major pipes.
1.3.3 Requirements for cooperation with electric
After the capacity of air conditioning unit is determined, check the following aspects with relevant
electric design personnel:
(1) Whether the electrical load is designed based on the requirement of the air conditioning unit;
(2) Whether the power cable and circuit breaker meet the unit requirement and abide by relevant
national safety regulations;
(3) Whether the regional power supply quality (including voltage fluctuation and interference noise)
meet the international requirement;
(4) Any nonconformity must be resolved through coordination.