6 Using the heating system – Performing a chimney sweep measurement
60
30.Make sure that all of the doors are closed.
31.Wait until the progress bar is full.
The Ready for ignition message appears in the display.
The HDG F20-50 boiler is ready for automatic ignition.
6.4 Performing a chimney sweep measurement
In Germany, there is a legal requirement that heating systems with
nominal thermal power in excess of 4 kW be inspected annually by a
qualified combustion engineer to see that federal emission limits for
small and medium-sized boiler systems are met (1st Federal Emission
Control Ordinance).
I
NITIAL TEST The operating company must notify the responsible combustion
engineer of the installation of the heating system before it is
commissioned, and must also arrange an appointment for the
chimney sweep test within four weeks of commissioning. To ensure
a stable operating ability, sufficient heat transfer must occur while
operating at full load.
T
EST EVERY TWO YEARS In Germany, regular inspections every two years must be carried out
in accordance with the requirements of the federal emission limits
(1.BImSchV).
Figure 6/20 - Closing the doors