6.  Commissioning / Service / Maintenance  
6.1  Checks before commissioning 
Before commissioning, the signals and electrical connections must be checked to guarantee that the 
components of the LMI system are working properly. 
 
•  Check that the boom angles displayed match the actual angles 
•  Check that the slew angle displayed match the actual slew angle 
•  Check that the crane radius displayed matches the actual radius 
•  Check the load display by lifting a known load  
 
 
If any of the displays shows any difference between the values displayed and the actual 
values, please contact your local service centre to have the LMI calibration checked or the 
system repaired.  
 
www.hirschmann.com  >  USA  >  Electronic Control Systems  >  Contact - ECS 
 
 
Following any modifications to the mechanical structure or changes to the load suspension 
devices, your loader’s LMI calibration needs to be checked or corrected.