COMMISSIONING
5.4.1 Commissioning Report
All settings both on boiler and burner will be recorded on
a commissioning report which will be supplied to the cus-
tomers representative.
Fig. 23
5.5 Hand-over to the user/safe-keeping
Obtain from the user a written statement that operating
and maintenance instructions have been explained to
him and he has received the relevant operating instruc-
tions (see page 60 for a standard statement). The system
designer is responsible for providing operating instruc-
tions for the complete system. This technical information/
installation instructions are not to be destroyed after com-
missioning but kept permanently with the system.