6 Power-On and Commissioning
● Wear personal protective equipment and use dedicated insulated tools to avoid
electric shocks or short circuits.
Before the equipment is put into operation for the rst time, ensure that the
parameters are set correctly by professional personnel. Incorrect parameter
settings may result in noncompliance with local grid connection requirements and
aect the normal operations of the equipment.
6.1 Check Before Power-On
No.
Expected Result
1 The EMMA is installed correctly and securely.
2 All cables are connected securely.
3 Power cables and signal cables are routed according to the
requirements for routing electrical and ELV cables and in compliance
with the cable routing plan.
4 Cables are bound neatly, and cable ties are secured evenly and
properly in the same direction.
5 There are no unnecessary adhesive tapes or cable ties on cables.
EMMA-(A01, A02)
User Manual 6 Power-On and Commissioning
Issue 05 (2024-01-19) Copyright © Huawei Digital Power Technologies Co., Ltd. 40