6 Power-On and Commissioning
D ANGER
Wear personal protective equipment and use dedicated insulated tools to avoid
electric shocks or short circuits.
NO TICE
Before the equipment is put into operation for the rst time, ensure that the
parameters are set correctly by professional personnel. Incorrect parameter
settings may result in noncompliance with local grid connection requirements and
aect the normal operations of the equipment.
6.1 Check Before Power-On
No.
Expected Result
1 The EMMA is installed correctly and securely.
2 All cables are connected securely.
3 Power cables and signal cables are routed according to the
requirements for routing electrical and ELV cables and in compliance
with the cable routing plan.
4 Cables are bound neatly, and cable ties are secured evenly and
properly in the same direction.
5 There are no unnecessary adhesive tapes or cable ties on cables.
EMMA-(A01, A02)
User Manual 6 Power-On and Commissioning
Issue 05 (2024-01-19) Copyright © Huawei Digital Power Technologies Co., Ltd. 40