Step 7 Reinstall the upper front panel.
Step 8 (Recommended) Install a lock for the maintenance bypass switch, as shown in
Figure 4-40.
----End
Rack-mounted Installation
NO TICE
The rack must comply with IEC 297. The rack depth is greater than or equal to
1100 mm. The distance between mounting bars on the same side must be
greater than 820 mm.
Reserve sucient clearance in the lower part of the rack for bottom cable
routing.
Step 1 Install guide rails (total height: 2 U) on the left and right sides at the lowest part
of the rack.
NO TICE
The UPS is heavy and cables are routed in from the bottom. You are advised to
install the UPS at the lowest part of the rack.
1. Level the bottom plane of a guide rail with the lower edge of U scale 01, and
engage the mounting ears on both ends of the guide rail into the mounting
holes of the mounting bar.
UPS5000-A-(30 kVA-120 kVA)
User Manual 4 Installation and Cable Connection
Issue 17 (2024-02-21) Copyright © Huawei Digital Power Technologies Co., Ltd. 96