Commissioning
After Installation Is Complete
In your own interest and for safety, in the United Kingdom, it is the law that all solid fuel appliances are
installed by competent persons, a registered installer or approved by your local building control ofcer. The
Heating Equipment Testing and Approval Scheme (HETAS) require its members to work to recognised
standards.
Door Tension Adjustment
The door tension latch is factory set to give the optimum pressure on the door seal. It should not normally need
any adjustment until after the stove has had some considerable use or has had the glass replaced. However,
after installation and before commissioning adjust the door latch tension if required. The latch tension is adjusted
by adding or removing the shim washers behind the outer door latch.
This will adjust the tension of the door seal against the stove body.
Air Supply
Whencommissioningthereensurethattheairsupplyisadequateforthere.Anairsupplymayberequiredin
homeswhichhavehighlevelsofairtightnessevenifthereoutputis5kWorless.Particularattentionshouldbe
observed if there is a ceiling fan or extractor fan in the room or adjoining room as this may have an effect on the
drawoftheue/re.Thereshouldbetestedwiththeceilingorextractorfanonandwithallinterconnecting
doors to the room closed and then open. If required additional air may be required to overcome the extractor or
fan pressure.
Smoke Draw Test.
Ensure appliance is not alight.
Warm chimney for 10 minutes using a blowlamp or similar heating device.
Placeasmokepelletinthewoodtrayorbasketgratetowardsthefrontoftheopeningofthereandignitethe
pellet.
Open the air control valve and close the door.
Checkthatthesmokeisbeingdrawnuptheueandthatitisdischargingsatisfactoryattheueterminal.
Ifthetestfailsthentheueandairsupplyshouldbechecked.Ifthiscannotberesolvedthenfurtherinvestigation
will be required or seek expert advice.
Lightthereasdetailedinthelightinginstructionsandallowtheappliancetoheatuptoitsoperatingtemperature
checking that no spillage occurs. There may be some fumes due to the burning off of protective oils and paint
curing. This should not be confused with spillage.
When the operating temperature has been reached, open the door slowly and carry out a spillage test with a
smokematcharound the door opening. Ifexcessivespillage occurs then theueandair supply should be
checked. If after further re-testing this cannot be resolved then further investigation will be required or seek
expertadvice.Advisethecustomernottousethereuntilexpertadvicehasbeensought.
20