JOHNSON CONTROLS
103
FORM 150.73-NM1
ISSUE DATE: 07/03/2024
6
Commissioning
Commissioning of this unit should only
be carried out by Johnson Controls Au-
thorized personnel.
Commissioning personnel should be thoroughly famil-
iar with the information contained in this literature, in
addition to this section.
Perform the commissioning using the detailed checks
outlined in the Installation and Start-Up Checklist or
use Form 150.73-CL2 as the commissioning procedure
is carried out.
Preparation: power off
The following basic checks should be made with the
customer power to the unit switched OFF.
Inspection
Inspect unit for installation damage. If found, take ac-
tion and/or repair as appropriate.
Refrigerant charge
Refrigerants classified as A2L refrigerant must be han-
dled in accordance with all governing regulations. Fail-
ure to meet this requirement can result in damage to
equipment, release of refrigerant into the environment,
contamination of the operating space for the equip-
ment, and pose a risk of personal injury or death. It is
the responsibility of any service technician or operator
to adhere to these requirements. For details, refer to ac-
cess Chiller A2L Refrigerant Application Data, Form
160.00-AD10.
Check that pressure is present in both systems and that
no leaks are apparent. If no pressure is present, a leak
test must be undertaken, the leak(s) located and re-
paired. Condensing units are supplied with a nitrogen
or refrigerant holding charge (see tag on unit). These
systems must be evacuated with a suitable vacuum
pump/recovery unit as appropriate to below 500 mi-
crons.
Care must also be taken to liquid charge slowly to avoid
excessive thermal stress at the charging point. Once the
vacuum is broken, charge into the condenser coils with
the full operating charge to provide 18°F subcooling.
Service and oil line valves
Open each compressor suction and discharge service
valve. If valves are of the back-seat type, open them
fully (counterclockwise) then close one turn of the
stem to ensure operating pressure is fed to pressure
transducers. Open the liquid line service valve and oil
return line ball valve fully in each system.
Compressor oil
To add oil to a circuit - connect a YORK hand oil pump
(Part No. 470-10654-000) to the 1/4 in. oil charging
valve on the compressor with a length of clean hose
or copper line, but do not tighten the flare nut. Using
clean oil of the correct type (“V” oil), pump oil until
all air has been purged from the hose then tighten the
nut. Stroke the oil pump to add oil to the oil system.
The oil level should be between the bottom and middle
of the sight glass. Check oil levels after operating the
system at full load. Turn off the system and check the
level. High oil concentration in the system may cause
nuisance trips resulting from incorrect readings on the
level sensor and temperature sensors. Temperature
sensor errors may result in poor liquid control and re-
sultant liquid overfeed and subsequent damage to the
compressor.
Fans
Check that all fans are free to rotate and are not dam-
aged. Ensure blades are at the same height when ro-
tated. Ensure fan guards are securely fixed.
Isolation / protection
Verify all sources of electrical supply to the unit are
taken from a single point of isolation. Check that the
maximum recommended fuse sizes given in Section 5:
Technical data has not been exceeded.
Control panel
Check the panel to see that it is free of foreign materi-
als (wire, metal chips, etc.) and clean out if required.
Power connections
Check that the customer power cables are connected
correctly to the terminal blocks or optional circuit
breaker. Ensure that connections of power cables with-
in the panels to the circuit breaker or terminal blocks
are tight.
Section 6: Commissioning