6.2 Requirements governing the installation site
Only install and assemble the unit if the following conditions are met:
Make sure that the wall/ceiling is sufficiently load-bearing to take the weight of the unit (Technical data [}12]).
Make sure that the ceiling is sufficiently load-bearing to take the weight of the unit (Technical data [}12]).
Make sure that the unit is securely suspended/standing.
Ensure that the airflow can circulate freely.
Provide adequate space for flow and return water connections on site (Connection to the pipe network [}30]).
There is a power supply on site (Maximum electrical rating values [}40]).
If need be, provide a condensation connection with a sufficient gradient on site.