Commissioning
5-2 820XBA1097
-
In case of condensation connect the controller to mains
voltage only after the visible humidity has evaporated.
-
The plug-in power terminals of the 820Xcontroller must only
be connected or disconnected when no voltage is applied.
Maintain the switch-on sequence!
5.2 Short set-up (Factory setting)
5.2.1 Switch-on sequence
Step
1.Switch on mains voltage
2.Select the direction of rotation.
-
CW rotation:
- Apply a LOW signal to terminal E4 (0...+3V).
-
CCW rotation:
- Apply a HIGH signal to terminal E4 (+12...+30V).
3.Select the setpoint. Apply a voltage 0...+10 Vto terminal 8.
4.Enable the controller. Applya HIGHsignal (+12...+30V) to terminal 28.
5.The drive is now operating according to factory
setting.