Commissioning
L
38
EDBEPM-H310 DE/EN/FR 2.0
4 Commissioning
4.1 First switch on
For commissioning, the system bus must be completely wired.
Stop!
Before switching on the supply vol tage:
Check the wi ring for completeness and short circuits,
Check whether the bus system is terminated physically at the first and last device.