Slurry Pump
WH15AM1AAA0EN_06B.DOC JAN 04-W51
Commissioning
1/1
7 COMMISSIONING
WARNING
BEFORE CARRYING OUT THE FOLLOWING CHECKS, ISOLATE THE ELECTRICAL SUPPLY TO THE
MOTOR.
1. If the pipework has not been connected to the pump on installation, ensure that the
pump case and associated pipework are clear of any construction debris, slurry etc.
before connection.
2. Ensure that the foundation and the securing bolts are tight.
3. Check that the rotating assembly is free to turn manually.
4. Check that the direction of rotation is correct -see General installation procedure,
section 6.4.4.
CAUTION
THE PUMP MUST NOT BE RUN IN THE OPPOSITE DIRECTION AS THIS COULD RESULT IN THE IMPELLER
UNWINDING FROM THE SHAFT, CAUSING EXTENSIVE DAMAGE TO THE PUMP.
5. Check lubrication.
NOTE: THE BEARINGS AND SEAL ASSEMBLIES ARE GREASE PACKED ON ASSEMBLY. SEE
LUBRICATION, SUB-SECTION 9.4.
6. Ensure that the openings on each side of the bearing frame and the area around the
gland are clear of debris, dried slurry, etc.
7. Check that all safety guards are secured in position.