COMMISSIONING
TECHNICAL DOCUMENTATION 29
MAXIMUM LOAD ADJUSTMENT
Press and hold the button for three seconds until the below display appears, the boiler will then start to
operate at minimum load.
To adjust to maximum rate, press and hold until the below display appears, the boiler will then start to
operate at maximum load.
MINIMUM LOAD ADJUSTMENT
Press and hold the button for three seconds until the below display appears, the boiler will then start to
operate at minimum load.
If the boiler is already operating at maximum load (displaying ‘t 100’), then press and hold until the
display reads as above.
To return to normal operating mode, press and hold for three seconds until the boiler returns to the
temperature display.