3.4.1 Inspection Before Trial Running
Before running test, confirm below items and write √ in block;
Correct unit installation
Power supply voltage is the same as unit rated voltage
Correct piping and wiring
Air inlet & outlet port of unit is unblocked
Drainage and venting is unblocked and no water leaking
Leakage protector is working
Piping insulation is working
Ground wire is connected correctly
3.4.2 Trial Running
Step 1:Running test can begin after completing all installation;
Step 2:All wiring and piping should be connected well and carefully checked, then fill water tank
with water before power is switched on;
Step 3:Emptying all air within pipes and water tank, press “on-off” button on control panel to run
the unit at setting temperature;
Step 4:Items need to be checked during running test:
• During the first running, unit current is normal;
• Each function button on control panel is normal;
• Display screen is normal or;
• Are there any leakage in the whole heating circulation system;
• Condensate drain is normal;
• Are there any abnormal sound or vibration during running?