PREPARING FOR FIELD LEVEL TESTING: Main Board Preparation 
2.7.2 Main Board Preparation 
 
Inspect the Main Board and verify that the following parts are not damaged, bent or defective. 
 
Tools Required: 
None Required 
 
1.  Lift the left of MB label and apply the Kapton Tape to the Top of the Main Board. 
2.  Apply the Main Board label. 
3.  Apply the sledgehammer Shield Cu Tape to the Main Board. 
4.  Apply the water indicator to the main board and ensure it is in the proper place.     
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
4
3 
2
1