Rotation operation
Equalizes the operation time by stopping the operation in order. This
prevents the operation time from being uneven depending on the
refrigerant system.
Stand by Operation Stand by OperationOperation
Stand by Operation Stand by Operation Stand by
System2
System1
• The rotation operation can be set only when controlling 2 refrigerant systems of
Single split system (combination of 1 outdoor unit and 1 indoor unit) by one remote
controller.
Backup operation
The backup operation is a support operation performed by a refrigerant
system in standby mode when the room temperature does not reach the
set temperature due to poor performance or occurrence of an alarm.
Example: When an error occurs while System 1 is in operation and System 2 is in
standby, System 2 will start up.
• In normal condition
Operation
Stand by
System2
System1
• When an error occurs in System 1
ErrorOperation
Stand by Operation
Power supply error or PCB error
System2
System1
Initial Settings
Rotation
Backup