19
Before the first and each further use, spray the plywood
formlining edges with, e.g. PERI Bio Clean. This ensures
easier shuttering and striking, and looks after the plywood.
Remove plywood and remaining cross beams and store in
pallets.
Accurately stack the plywood formlining in order to be
able to clean the stacked sheet edges.
Remove main beams and store in pallets. Take prop load into
consideration!
In those cases where the formwork is not dismantled or if
back-propping is used, concreting of a slab above could lead
to overloading of the props.
Remove the Crosshead props and store them in pallets.
– For horizontal transport, the heads stay attached to
the props!
– Accurately stack the plywood formlining in order to
be able to clean the stacked sheet edges.
45
67
A5 Striking
MULTIFLEX Girder Slab Formwork
Assembly Instructions for Standard Configuration