Mixing pump RITMO L / RITMO M Overview - Operation
Maintenance work
68
2016-02-17
4. Also blow out the air filter housing with compressed air, so as to
remove dirt particles.
5. Abrasion at the housing wall subjects the sliders to wear and tear.
6. Check the slider width after 3000 operating hours or annually; it
should be at least 12.5 mm.
7. At the time of replacing, blow the housing with dry compressed
air.
50.7 Actions after completed maintenance
1. After finishing the maintenance works and prior to switching on
the machine, the following steps have to be carried out:
2. Check all previously loosened screw connections for secure fit.
3. Check if all previously removed safety systems and covers are
properly reinstalled.
4. Ensure that all used tools, materials and other equipments were
removed from the work area.
5. Clean the work area and remove any spilled materials such as
liquids, processing material or similar.
6. Ensure that all safety systems of the installation work perfectly.