Commissioning
Operating Manual PSENvip RL D P Set
1001641-EN-09
| 85
The test piece interrupts the advance measuring field. The press stroke is stopped. The up-
per tool should not touch the test piece.
} Once the press stroke has stopped, push the 15 mm high section of the test piece be-
neath the upper tool.
The upper tool should not touch the test piece.
Function test using the 35 mm test piece
} Start up the press.
} Position the 35 mm high section of the test piece on top of the lower tool.
} Initiate a press stroke.
The test piece interrupts the advance measuring field. The press stroke is stopped. The up-
per tool should not touch the test piece.
7.5.2 Visual inspection
Check the following on the PSENvip transmitter and receiver
} The condition of the installation and attachment
} Any damage on the housing and lens
} Electrical connections
} Switch on the machine.
} Check the messages on the display.