For maritime shipment, the equipment is packed assembled vertically, in a cardboard box and fixed on
a pallet base with screws at four steel brackets. Externally the box is strapped and shrink-wrapped.
In case of air shipment, the charger is shipped lying down in a wooden box.
The equipment is ready to be handled by forklift truck and be transported by truck or container. Keep in
mind the load distribution and center of gravity.
For handling, the equipment has four lifting rings at the top. The image below (top view) shows the
location of the four lifting points.
Be aware of all caution and warning messages before lifting the equipment.
To lift the equipment, a sling or a chain must be attached to each ring and securely fastened to the crane.
The following image shows an example of lifting the equipment with slings: