7. SCHEDULED MAINTENANCE
The UPS while its lifetime requires scheduled maintenance cycles to maintain operating reliability and
efficiency.
Scheduled maintenance must be performed by the company which provided the machine or company
specialized and trained on the system by the seller.
7.1. ANNUAL MAINTENANCE (OR PERFORMED EVERY SIX MONTHS IN THE CASE OF UNITS IN
CRITICAL APPLICATIONS)
The following actions and tests are performed while the scheduled maintenance:
cleaning the machine
cleaning the control logic and interface boards
checking the tightening of all nuts and bolts and electrical connections (UPS and battery)
testing the ventilation efficiency
testing the inverter output wave form
testing output voltage / frequency
testing synchronization
testing signals, alarms and EPO tripping
display calibration with calibrated instrument
operating test of manual switches and automatic devices
operating test of switching circuits
power failure test of UPS line, battery efficiency test and test of correct battery charger operation.