52
LPG Solenoid Valve, If equipped
___ Check to be certain there is a transient voltage suppressor installed in the valve, under a section of
heatshrink, where the two black wires enter the valve.
___ Check that port A (N/C) of the valve is connected to the vent line check valve of
the vapor release.
___ Check that port B (Common) of the valve is connected to the top of the meter differential valve.
___ Check that port C (N/O) of the valve is connected to line pressure.
System
___ Check to see that the E4000 LCD Display turns on automatically when the truck ignition is ON.
___ Congure the E4000.
___ Set the BATCH mode in the Supervisor menu to program the correct valve operation.
___ Set the COM PORTS mode in the SUPERVISOR menu, for the PRINTER, to BAUD RATE - 9600,
PARITY - NONE, and HANDSHAKING - HARDWARE.
___ Verify printer wiring is correct by printing a calibration report.
___ Verify HHC wiring is correct by using the Neptune E4000 Conguration Software to download a
conguration from a computer to the E4000.
___ Pump product thru the meter and verify the E4000 operates correctly.
___ Zero the RML 2000.
___ Calibrate the system.
E4000 Serial No. _________________________
Date Installed ___________________________
Installed By_____________________________
Checked By ____________________________