J Line Pump
Horizontal Double Suction Centrifugal Pump – API 610 Process Pump
115 V1.032818
45. Insert the first axial bearing over the shaft from the non-coupling side until it reaches the
axial bearing spacer.
Figure 8.43JD. Inserting the first axial bearing over the shaft from the coupling side.
46. Insert the second axial bearing facing backwards over the shaft from the non-coupling side
until it reaches the first axial bearing.
Figure 8.44JD. Inserting the second axial bearing backwards over the shaft from the non-coupling side.
The bearing must be heated to 100 °C / 212 °F. The bearing must be passed 3
times over the heater to demagnetize them. This should be done for the proper
installation and function of the bearing.