42. Manually place and tighten the coupling nut over the shaft from the coupling side.
Figure 8.41. Placing and tightening the coupling nut over the shaft from the coupling side.
43. Manually place and tighten the hex bolts to secure the internal radial bearing housing cover
to the radial bearing housing.
Figure 8.42. Placing and tightening the hex bolts to secure the internal radial bearing housing cover to the radial
bearing housing.