NOTE:
Prior to installing the heat exchanger tubing into push lock fitting
ensure that any sharp edges are removed to avoid cutting the
O-ring and generating a compressor leak. A compressed air leak
will cause the ATF performance to degrade quickly. This will
result in premature unit failure.
6.6.5 Install the heat exchanger and air inlet hose.
6.6.6 If the compressor was removed, re-install according to the compressor removal and installation
procedure. (New Spring/Bolt hardware is available upon request)
6.6.7 Start the unit and check for leaks. If compressor is noisy refer to section 5.7 for
troubleshooting.
6.6.8 Shut down unit and install covers.