Safety Precautions
xii
Measures during Power Outage
Take the following measures in the event of power outage.
1 Immediately stop the supply of hydrogen gas.
2 Switch OFF power to the GC and the MS.
3 Open the windows and doors of the room where the instrument is installed
to thoroughly ventilate.
4 Confirm that there is no ignition source in the room that could ignite the
hydrogen gas.
5 Wait until the temperature of all GCMS-QP2010 Series, GCMS-QP2020,
GCMS-TQ Series components has fallen to the ambient temperature
(approximately 1 hour).
6 Open the front door of the GC and loosen the nut of the interface to return
the interior of the MS to atmospheric pressure.
7 Confirm that the knob on the front door of the MS is completely loose.
8 Wait until all hydrogen gas is completely expelled (approximately 30
minutes).
9 After confirming the items in "Precautions in Installation" and "Precautions
in Operation and Running of the Instrument", use the standard startup
procedure to start the GC and MS.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Shimadzu GCMS-QP2020 and is the answer not in the manual?

Shimadzu GCMS-QP2020 Specifications

General IconGeneral
BrandShimadzu
ModelGCMS-QP2020
CategoryLaboratory Equipment
LanguageEnglish

Related product manuals