3. Installation and Debugging
This series of models only could be applied in working environment with good
ventilation.
Make a careful study of this chapter before installation. The machine must be
installed according to the steps below.
Power supply should be connected by qualified electricians.
3.1 Installation of SAL-430 / 460
Picture 3-1: Installation Methods (SAL-430/460)
1. Notes for Installation and Positioning
1)
Machine just can be mounted in vertical position. Make sure theres no
pipe, fixed structure or other objects above the installing location and
around the machine which may block machines installation, hit objects or
injure human person.
2) For easy maintenance, its suggested to leave 1m space around the
machine.
3) Machine should be placed on water-level surface. If it needs to be
mounted on a higher surface (e.g. the scaffold or the interlayer), should
ensure its structure and size could bear the weight and size of the
machine.