Accessing the connection compartment through the rear
182 NXAIR M 139-2021.9 / 07
Fig. 313: Inserting the rear wall and pushing it down
Insert the 2 sealing brackets (3) into the vertical gaps between the panels.
Install the horizontal ledge (4). Fix it by screwing the bolts in hand-tight:
8 bolts M8x25 with contact washers and plain washers size 8
acc. to ISO 7093
Tighten the bolts with torque 25 Nm.
Install one of the vertical ledges (5). Fix it by screwing the bolts in hand-tight:
14 bolts M8x20 with contact washers
Tighten the bolts with torque 25 Nm.
Proceed in the same way with the other vertical ledge.
Fig. 314: Installing ledges and brackets
The rear wall is installed on the connection compartment.