9.2 Checking the controller parameters
Optimum adjustment of the controller to the controlled system can be checked by
recording a startup sequence with the control loop closed. The following diagrams
indicate possible incorrect adjustments, and their correction.
The response to a setpoint change is shown here for a 3rd order controlled system for
a PID controller. The method used for adjusting the controller parameters can,
however, also be applied to other controlled systems. A suitable value for dt is rt/4.
Pb too small Pb too large
t
x
w
7865d17/1099
Figure 27: Pb too small
t
x
w
7865d15/1099
Figure 28: Pb too large
rt, dt too small rt, dt too large
t
x
w
7865d16/1099
Figure 29: rt, dt too small
t
x
w
7865d14/1099
Figure 30: rt, dt too large
Optimum adjustment
t
x
w
7865d18/1099
Figure 31: Optimum adjustment