CPU 1516pro-2 PN (6ES7516-2PN00-0AB0)
70 Operating Instructions, 11/2019, A5E35873416-AC
8.1 Overview
Introduction
This section includes information on the following topics:
● Procedure for commissioning the ET 200pro distributed I/O system with CPU
● Commissioning the CPU 1516pro-2 PN on PROFINET IO
● Inserting/replacing the SIMATIC memory card
● Operating modes of the CPU
● CPU memory reset
● Backing up and restoring the configuration
● Identification and maintenance data
● Shared commissioning of projects
Commissioning requirements
Note
Performing tests
You must ensure the safety of your plant. You therefore need to perform a complete
functional test and the necessary
safety checks before the final commissioning of a plant.
Also allow for any possible foreseeable errors in the tests. This
avoids endangering persons
or equipment during operation.
Software tools for commissioning
The following free software tools support you in commissioning:
● SIEMENS PRONETA in commissioning PROFINET systems.
● SIMATIC automation tool in commissioning the CPU 1516pro-2PN..
You can find more information on SIEMENS PRONETA and the SIMATIC Automation Tool
in the section AUTOHOTSPOT