Commissioning
8.2 Procedure for commissioning the ET 200pro distributed I/O system with CPU
CPU 1516pro-2 PN (6ES7516-2PN00-0AB0)
Operating Instructions, 11/2019, A5E35873416-AC
71
8.2 Procedure for commissioning the ET 200pro distributed I/O system
with CPU
8.2.1 Introduction PROFINET IO
Requirements
The CPU is in the "Factory settings" state or has been reset to factory settings (see
section Resetting the CPU to factory settings (Page 101)).
The SIMATIC memory card is as delivered or has been formatted.
At the startup of the station with CPU 1516pro-2 PN, the installation must be complete. All
bus, solid-state, connection modules and the termination module must be mounted.
Note
Interfaces for operation of the CPU as IO controller or IO device
You can operate the CPU
1516pro-2 PN via both interfaces (X1 and X2) as an IO controller
or IO devic