Commissioning
4.5 Commissioning with STARTER
Inverter with CU240B-2 and CU240E-2 Control Units
Operating Instructions, 07/2010, FW 4.3.2, A5E02299792B AA
81
● Click on "Load hardware configuration to PG" to save the online setup to your PC and
create an online link between the inverter and PC.
● To conclude your entry, choose "Close".
● The status display changes from the "Offline mode" with blue background into the "Online
mode" with yellow background.
Note
If you click on "Close" without having first run "Load hardware configuration to PG", the
data is not saved and the inverter remains offline.
4.5.7 Basic commissioning
In the online state, open the STARTER screen of
the Control Unit with a double click and there click
on the "Wizard" button.