Commissioning   
6.3 Adjustment and initial commissioning 
  SIWAREX WL200 
36  Operating Instructions, 07/2016, A5E02199611B-03 
1.  Measure the output resistances R
o
 of the load cells LC. Alternatively: Use the values from 
the corresponding data sheet. Example: 
 
LC 2:  1003.64 Ω 
2.  Place the test weight on all four corners: Note the measured values 
 
3.  Determine the differences from the smallest value: 
 
1)