Chapter 2. Installation and System Checkout
2-16
Depleted Battery Cutout
For depleted battery cutout, remove the jumper shown in
Figure 2-17 from the main system board. If you are using an
Expansion Power Supply (EPS), you must also remove
Jumper R76 from the EPS. (When programming the panel,
make sure to enable the Depleted Battery Cutout system
option.)
Safety Ground/Ferrite Bead
Proper operation and protection against transient energy per
UL864 and ULC-S527 requires connection of safety ground
wire to cabinet chassis as shown in Figure 2-18.
In addition, a ferrite bead must be attached to the incoming
AC power line as shown in the figure. Wrap the LINE and
Neutral legs of the power line twice through the ferrite bead.
System Powerup and Checkout
Use the following procedure to apply AC and battery power
to the 4006.
On power up, the panel performs the following:
Displays revision of boot-loader software
CPU self test
Link Scan - checks for a programming unit connection
Memory Test - Verifying system and job-specific soft-
ware
Startup - 4006 Exec startup
If the panel successfully completes its start up self-test, it
will indicate a warm or cold start trouble, which clears when
acknowledged. If there are no other troubles in the system,
the following is displayed:
SYSTEM NORMAL
12:00 am 21-FEB-03
If other troubles exist in the system, the following is dis-
played:
FIRE | SUPV | TRBL
00 | 00 | 02
Pressing the <TROUBLE ACK> key allows the operator to
acknowledge the troubles (silencing the panel sounder) and
scroll through the troubles on the active Trouble List.
If the 4006 self-test fails, the panel displays an error code
and waits 30 seconds before attempting a restart.
Acceptance Testing
When you are finished with the original installation, pro-
gramming and all modifications, conduct a complete opera-
tional test on the entire installation to verify compliance with
applicable NFPA standards and Local Codes. Testing should
be conducted in the presence of a representative of the
Authority Having Jurisdiction (AHJ), and the customer's
representative. Follow procedures outlined in Chapter 10
“Inspection, Testing, and Maintenance” of NFPA standard
72-2002 and as dictated by local codes.
Testing Circuit Supervision
Use the following procedures to confirm that IDCs and
NACs are supervising for opens, shorts and grounds. The
right column in this table shows the LEDs that illuminate
when an open, short, or ground occurs on a specific circuit.
Figure 2-17 Location of Depleted Battery Jumper
Figure 2-18 Safety Ground and Ferrite Bead
LINE NEUTRAL
BATT EPS
+ - + -
Remove this
Jumper