36 EN
MASTERYS BC+ 10-40 kVA - IOMMASBCXX0G-EN 02 - SOCOMEC
9. OPERATING PROCEDURES
NOTE: before carrying out any operations on the unit read the 'Safety standards' chapter carefully.
NOTE: with the stop procedure the load will be disconnected.
9.1 Switching ON
• Connect the mains and auxiliary mains to the UPS.
• Wait until display switch on.
• Enter MAIN MENU > CONTROLS > PROCEDURES.
NOTE: In parallel configuration the procedure must be performed from the system menu.
• Select START PROCEDURE and press ENTER.
• Carry out the operations indicated on the display.
9.2 Switching OFF
This operation interrupts the power supply to the load. The UPS and the battery charger will be shut down.
• Enter MAIN MENU > CONTROLS > PROCEDURES.
NOTE: In parallel configuration the procedure must be performed from the unit menu.
• Select STOP PROCEDURE and press ENTER.
• Wait approx. 2 minutes for the UPS shutdown.
NOTE: the controlled shutdown of each server connected to the LAN can be managed by shutdown
software.
• Carry out the operations indicated on the display.