Testing the RM-DCM-2
33
Testing the RM-DCM-2
This section describes the procedures that verify the RM-DCM-2
installation and operation.
Required Equipment
The following equipment is required.
Two 1K resistors
An LCD display module (2 line x 16 character), Software House part
number RM-LCD
Three LEDs
A multi-meter to measure voltage and resistance
Configuration Requirements
You must complete the following configuration requirements before you
test the RM-DCM-2:
1. Install the RM-4E.
2. Install the LCD display module into the LCD connector on the RM-4E circuit
board.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Software House RM-DCM-2 and is the answer not in the manual?

Software House RM-DCM-2 Specifications

General IconGeneral
BrandSoftware House
ModelRM-DCM-2
CategorySecurity System
LanguageEnglish