Isolation Fault Alarm
Enter the setting interface to follow the instructions when it is first time to
start up.
The isolation fault alarm installed into the inverter, is the standard
configuration, as required by AS 4777_2020 and New Zealand, it will give
a visual alarm once the isolation impedance of the PV arrays is less than
20 KΩ.
The error indicator light will be in red and the control panel will display
isofault.
WARNING!
Power to the unit must be turned on only after installation
work has been completed. All electrical connections must be
carried out by qualified personnel in accordance with
legislation in force in the country concerned.
NOTE!
Please set the inverter according to local requirements.
50
51
Commissioning
Please select Australia Region A, B, C for power quality response modes
and grid protection settings during commissioning.
You can adjust setpoints for power quality response modes and grid
protection settings if required.
After commissioning, you can view the following settings through the LCD
of the inverter after commissioning:
Firmware version
Region settings (and setpoints) for grid protection settings
Region settings (and setpoints) for power quality response modes.
NOTE!
Once settings are selected at commissioning they are
locked to view only.
NOTE!
Password should not be readily available – if you need
that, you can find the password that either in
a separate maintenance/service manual or available from
manufacturer/importer upon request