UM0027_ SOL APOLLO Series 7.4-22K_EN_V02_0523 29
5 Mounting
5.1 Planning the Installation
5 Qualified Person
Installing and connecting the product must be done by a qualified electrician.
Laws and regulations, relevant to the country of installation, regarding the
safety of persons, animals, and property must be observed. A typical planning
procedure may include but are not limited to the following:
1. Calculate the existing electrical load to determine the maximum operating
current.
2. Calculate the appropriate cable size with respect to distance to minimize
voltage drops.
3. Obtain any necessary permits from the local authority that has jurisdiction
and confirm that the follow-up inspection has been scheduled by a quali-
fied electrician after the installation is complete.
4. Use only copper conductors.
5. Use conductors that are sized in accordance with local wiring regulations.
The selected cable gauge must be able to sustain periods of a constant
load up to 16A / 32A.
6. Each unit should be connected to an appropriately sized circuit breaker.
7. Knowledge of the current capacity of the site (in amperes).
5.2 Site Requirements
1. Ensure the product is installed out of reach from children.
2. Ensure appropriate access to the product for installation and maintenance.
3. Ensure there is adequate heat dissipation by observing the minimum
clearance to walls, other EV chargers or objects:
Direction
Min. Clearance (mm)
above
200
below
200
sides
200